energyRe sells 317 MWdc South Carolina solar to Enel Green Power
Enel Green Power North America will take full ownership of a roughly 317 MWdc South Carolina solar portfolio from energyRe in a deal expected to close in the first quarter of 2027.
By Daniel Okafor
3 min read

What's News
- Enel Green Power North America will acquire full ownership of a roughly 317 MWdc utility-scale solar portfolio in South Carolina from energyRe
- Transaction expected to close in the first quarter of 2027, subject to customary closing requirements and required U.S. regulatory approvals
- Financial terms were not disclosed
- energyRe remains construction manager and oversees the projects through commercial operation
- energyRe has broken ground on about 450 MW over the past year and has nearly 700 MW operating or in late-stage development
Enel Green Power North America has agreed to acquire full ownership of a portfolio of utility-scale solar projects in South Carolina representing approximately 317 MWdc of new generating capacity, according to energyRe. The transaction is expected to close during the first quarter of 2027. Financial terms were not disclosed.
Closing depends on customary closing requirements and required U.S. regulatory approvals. For energyRe, the deal turns a South Carolina development pipeline into a signed sale while the company keeps a construction mandate on the same assets.
What changes hands in South Carolina?
The projects total roughly 317 MWdc of new generating capacity spread across the state. Enel Green Power will acquire full ownership of the portfolio. energyRe developed the assets and will now transfer them to the buyer.
Terms of the sale are thin. energyRe disclosed no purchase price, no financing structure and no project-by-project breakdown of the 317 MWdc. The portfolio moves as one block to a single owner, and no construction milestones were laid out in the announcement.
The deal gives Enel Green Power a utility-scale position in South Carolina and leaves energyRe in place as construction manager through the build-out.
What did Ryan Brown say?
Ryan Brown, Chief Operating Officer at energyRe, called the deal proof of the development work. "This transaction is a strong validation of the projects we have built in South Carolina and of the team that developed them. Enel Green Power is a world-class owner and operator, and we are pleased to hand these projects to a partner that shares our commitment to delivering reliable, affordable power to South Carolina homes and businesses. Our team will remain on the ground as construction manager to see these projects through to commercial operation."
Brown's statement carries two claims: the projects reached a standard Enel Green Power will accept, and energyRe's own team stays on them after the sale. The second point matters more to energyRe than the endorsement does, because it extends the company's involvement well past the transfer of title.
Why does the closing sit in 2027?
Three conditions shape the timetable: customary closing requirements, required U.S. regulatory approvals and the state of construction. energyRe will remain involved as construction manager and oversee the projects through commercial operation, so ownership transfer and plant completion run on two separate clocks rather than one.
The 317 MWdc represents capacity that has not yet reached commercial operation, and the retained role covers the gap between closing and commissioning. A first-quarter 2027 close therefore depends on regulators, not on the last panels going in.
How large is energyRe's pipeline?
The South Carolina portfolio is one piece of a wider build-out. By the company's own count:
- Approximately 450 MW of projects broken ground on during the past year
- Nearly 700 MW either operating or in late-stage development
- More than 1.8 GW across 20 projects in South Carolina, North Carolina, Nebraska and Oklahoma
- Generation, transmission and energy-storage infrastructure developed to address rising electricity demand
Set against the 450 MW broken ground over the past year, the 317 MWdc portfolio equals about seven-tenths of a year's construction starts. The 700 MW either operating or in late-stage development sits outside this sale, and energyRe's construction mandate applies to the 317 MWdc block.
energyRe develops generation, transmission and energy-storage infrastructure intended to address rising electricity demand, and this structure narrows the company's ownership exposure while keeping it in the build chain.
What to watch
The near-term checklist is short: U.S. regulatory approvals, satisfaction of customary closing requirements, and a first-quarter 2027 closing. Commercial operation, not closing, is the date that matters for delivered power, and energyRe stays on the ground until it arrives.
For energyRe, the test is whether a construction-management role carries the relationship once ownership moves to Enel Green Power. For the buyer, it is whether the 317 MWdc reaches commercial operation on schedule.
Source: pulse2.com
More from Daniel Okafor
Show full bio
Correspondent covering money, funding and market shifts around entrepreneurship, startups and venture funding at Business Bearings.