Google Buys 50 MW of Superhot Geothermal From Quaise at Obsidian
Google signed for 50 MW of superhot geothermal power from Quaise's Obsidian project in Oregon, with first deliveries targeted for 2030 — only the first phase of a 1 GW-plus roadmap.
By Grace Kim
3 min read

What's News
- Google agreed to buy 50 MW of superhot geothermal electricity from Quaise Energy's Project Obsidian in Central Oregon, announced November 17, 2026, with deliveries targeted as early as 2030.
- Obsidian's roadmap: 50 MW in Phase I (the only phase Google contracted for), 250 MW in Phase II and more than 1 GW in Phase III.
- Quaise targets 300–500°C rock and estimates up to 10 times more clean power per well than traditional geothermal, whose hot-water reservoirs rarely exceed 400°F.
- Google counts more than 240 clean-energy agreements signed from 2010 through 2025 for nearly 35 GW, including 148 North American projects above 29 GW, and more than $7 billion invested in Oregon over 20 years.
- Quaise projects 200 to 400 construction jobs and more than 50 permanent engineering and operations jobs at Obsidian.
Google agreed to buy 50 megawatts of superhot geothermal electricity from Quaise Energy's Project Obsidian in Central Oregon, a contract the company announced on November 17, 2026, with deliveries targeted to begin as early as 2030.
The power goes to Google's existing data centers in The Dalles and to communities in the region. Quaise describes the output as always-on and carbon-free once the plant is operating, and the deal gives Google a prospective source of firm clean generation for an established data-center base.
Google has been building in Oregon for two decades. It opened its first owned-and-operated data center in The Dalles in 2006 and now runs three data-center campuses there, along with an Oregon Cloud region and a Portland office. The announcement puts Google's Oregon investment at more than $7 billion over the past 20 years.
What did Google actually buy?
Only the first phase. Google's purchase covers the 50 MW of Obsidian's Phase I. The project roadmap lists 50 MW in Phase I, 250 MW in Phase II and more than 1 GW in Phase III, and Quaise says those later capacities belong to its expansion plan rather than to additional purchases under this contract.
The signed deal is a small piece of a much larger buying machine. Google counts more than 240 agreements signed from 2010 through 2025 to buy nearly 35 GW of new clean energy. Within North America, that list includes 148 projects representing more than 29 GW.
Google says it pays for all electricity used by its data centers and covers infrastructure needs directly driven by its growth.
In plain terms, Quaise has sold its opening tranche and still has to line up buyers for the other 1.2 GW-plus it has mapped.
Why millimeter-wave drilling matters
Phase I uses conventional drilling to reach superhot conditions at commercial scale. Obsidian is designed around underground temperatures of 300–500°C, and Quaise estimates that superhot geothermal can produce up to 10 times more clean power per well than traditional geothermal, which relies on naturally occurring hot-water reservoirs that rarely exceed 400°F.
The second phase is where the technology risk sits. Quaise expects Obsidian's Phase II to be "the first worldwide to use millimeter-wave drilling," a non-contact process that uses high-power microwaves to break down rock.
The equipment is designed to connect to existing drilling rigs and to make access to superhot heat economical. That is how Quaise argues the method can reach conditions beyond the limited locations suitable for conventional geothermal.
In plain terms, Phase I has to prove the wells, and Phase II has to prove the drilling method.
What does Obsidian mean for Oregon?
Quaise projects 200 to 400 construction jobs and more than 50 permanent engineering and operations jobs at Obsidian. Associated grid upgrades are expected to strengthen local reliability, while royalties from electricity sales are intended to provide lasting economic benefits for the region.
The arrangement lands in the same town where Google already operates three data-center campuses, so the grid work and the royalty commitments sit next to load that Google has been adding since 2006.
In plain terms, the local upside is jobs plus royalties, and the local obligation is a grid build-out on a 2030 schedule.
What has to work next
Most of the value in this deal is an option on technology rather than on volume. Quaise says technology proven at Obsidian is expected to lower development costs for later U.S. superhot geothermal projects, and the larger buildout — 250 MW in Phase II and more than 1 GW in Phase III — depends on that proof.
For data-center power, the milestone isn't the 50 MW. It's whether the first phase establishes commercial superhot production and whether the millimeter-wave approach can support the much larger expansion Quaise has drawn up.
Google's first 50 MW arrives in 2030 if the well program works, and Quaise's road to a gigawatt-plus project runs through a drilling method no one has yet used at commercial scale anywhere in the world.