Senate Passes Energy Permitting Overhaul 62-33, Data Center Grid Fees Head to House
The Senate's 62-33 vote on BAAJA mandates FERC ratepayer protections for data centers above 20 MW, with an estimated $35 billion in new grid fees over a decade.
By Daniel Okafor
4 min read
What's News
- Senate passed BAAJA 62-33 on Thursday, with 47 Republicans and 14 or 15 Democrats in favor
- Data centers over 20 MW must pay for grid upgrades; Grid Strategies estimates $35 billion collected over ten years
- Legal challenges to projects compressed to a 150-day window under NEPA, Clean Water Act and Endangered Species Act
- BloombergNEF counts ~100 GW of planned behind-the-meter gas at data centers; Earthjustice counts 177 GW
- Studies project 17–325 GW of added clean capacity by 2035–2040 and household bills $50–78 lower
The U.S. Senate passed the most significant overhaul of federal energy permitting in decades on Thursday, in a 62-33 vote that now sends a fight over data center electricity costs to the House.
The Bipartisan American Affordability and Jobs Act (BAAJA) drew 47 Republicans and 14 or 15 Democrats. Sens. Shelley Moore Capito (R-W.Va.), Mike Lee (R-Utah), Martin Heinrich (D-N.M.) and Sheldon Whitehouse (D-R.I.) negotiated the bill weeks before midterm elections handed Democrats control of both chambers. President Trump endorsed it, calling it a "BIG WIN for U.S. ENERGY INDEPENDENCE and DOMINANCE."
What does the bill actually change?
BAAJA shortens environmental review deadlines under the National Environmental Policy Act (NEPA), limits the alternatives agencies must consider, and narrows which projects trigger review at all. It compresses the window to file legal challenges to 150 days. It also restricts courts' power to halt projects — even when a review is found deficient — under NEPA, the Clean Water Act and the Endangered Species Act.
The bill expands the Federal Energy Regulatory Commission's authority to approve construction permits for interstate transmission lines when states block or delay them. It accelerates permitting for geothermal, hydropower, offshore wind and renewables. It removes federal permit requirements for onshore oil and gas drilling on non-federal land.
So-called "permit certainty" provisions bar future administrations from vacating issued permits except in emergencies. They also let developers sue agencies for "disparate treatment" of energy technologies.
How does it make data centers pay?
The most politically charged provision directs FERC to establish ratepayer protections for data centers above 20 megawatts. Those facilities must pay for grid upgrades they necessitate and for their use of existing transmission.
Grid Strategies estimates the changes would collect an additional $35 billion from data centers over ten years — $55 billion total.
"Data centers create well-paying jobs, generate substantial tax revenue, advance innovation, can lower electricity rates for other ratepayers," the Data Center Coalition said in a statement.
Where is the loophole?
The bill says nothing about behind-the-meter generation. McKinsey found 60% of North American data center operators plan on-site power plants, mostly gas-fired, to bypass grid interconnection queues. BloombergNEF counts roughly 100 gigawatts of gas capacity planned at data centers; Earthjustice puts the figure at 177 GW. If built, nine of the ten largest U.S. power plants would serve data centers on-site.
"The bill is not addressing that at all," said Meg Slattery of Earthjustice. "The models that model the emissions impacts of the bill do not account for behind-the-meter generation."
What do the emissions models say?
Four major modeling studies project BAAJA would add 17–325 GW of clean capacity by 2035–2040. Power-sector emissions cuts vary sharply by study:
- Rhodium Group: 1–18% by 2040; Resources for the Future: 6–15% across timeframes
- C2ES/Greenline Insights: 13% by 2035; SEIA: 20% cumulative reductions 2028–2035
- Rhodium: economy-wide cuts of 5–148 million metric tons CO2e annually by 2040, with household bills $50–78 lower
- Resources for the Future: 3.5–7% lower power system cost
The same models cut both ways. Rhodium's "High Emissions" scenario shows up to 8 GW more gas capacity and 8–15% higher LNG exports, with overseas combustion emissions uncounted. Resources for the Future projects a near-term increase in combined-cycle gas plants. All four studies cover only modeled provisions, not the full bill.
Why did Democrats split?
Sens. Jeff Merkley and Ron Wyden (D-Ore.) pushed amendments to ban data centers on federal land and block the Trump administration from canceling clean energy grants. Republican leaders blocked votes on all amendments. Sens. Raphael Warnock (D-Ga.) and Alex Padilla (D-Calif.) voted no.
Sen. Catherine Cortez Masto (D-Nev.) voted yes but said the bill "ignores Tribal input" — though Latitude Media reported she voted no over tribal consultation provisions, a discrepancy the sources do not resolve.
"This bill doesn't just roll out the red carpet for data center developers, it puts them on a greased-up slide into towns across America," Sen. Ed Markey said.
The Oneida Nation said the bill "threatens the tribe's ability to protect its sacred spaces, ancestors, traditional ceremonies and culture." Former Energy Secretary Jennifer Granholm countered that recent changes "strengthen protections for tribal consultation and restore important state authority over water quality."
What happens in the House?
The House passed a narrower, industry-friendly permitting bill last year. Rep. Scott Peters (D-Calif.) urged passage: "There will be no better deal on the table... With Donald Trump in the White House and 60 required votes in the Senate, bipartisanship is unavoidable." Reps. Jared Huffman (D-Calif.) and Rashida Tlaib (D-Mich.) argue Democrats should wait for the new Congress.
The House may amend the bill, which would force another Senate vote. Trump has signaled he would sign it. Whether the data center grid-cost provisions survive intact — and whether the behind-the-meter gas loophole gets closed — remains unresolved.