Stockland’s 444 MW Kemps Creek Data Center Enters Public Review

Stockland’s 444 MW Kemps Creek proposal entered NSW public review, not construction approval, with a 1.3 PUE ceiling and renewable-power matching required.

By Daniel Okafor

4 min read

Stockland’s 444 MW Sydney Data Center Plan Enters Public Review
Stockland’s 444 MW Sydney Data Center Plan Enters Public Reviewwal_172619 / pixabay

What's News

  • Public exhibition began November 19, 2026, with submissions due December 17, 2026.
  • The two-building campus has a maximum power consumption of 444 MW and allows up to 360 MW of IT load.
  • The EIS must demonstrate PUE of 1.3 or less and renewable-energy matching at all times.
  • Stockland owns 50% of Kemps Creek and reports roughly 450 MW secured across its platform.
  • Wetherill Park has about 238 MW of capacity; 192 Narellan Road is a 100 MW proposal.

By Daniel Okafor

The NSW Planning Portal lists a stated maximum power consumption of 444 MW for Stockland Development’s proposed Aldington Road Data Centre, which entered public exhibition on November 19, 2026. The two-building Kemps Creek campus accepts submissions until December 17, 2026.

Exhibition marks a review step, not permission to build. The portal says the State Significant Development remains under assessment, with the environmental impact statement (EIS) now before the public. Stockland’s October 19, 2026 operational update says Kemps Creek is 50% Stockland-owned and targets AI and hyperscaler customers.

What does the 444 MW proposal include?

The amended Planning Secretary’s Environmental Assessment Requirements (SEARs), issued on September 15, 2026, set out:

  • IT power consumption of up to 360 MW.
  • Data hall buildings as tall as 36.4 meters.
  • Ancillary offices, backup power and diesel storage.
  • A substation with distribution capacity of up to 1,000 megavolt-amperes.

The 360 MW figure applies to computing equipment, while the portal’s 444 MW figure covers the campus-wide maximum, including supporting infrastructure whose demand the EIS must quantify. On the current documents, that creates an 84 MW gap between the computing allowance and the campus ceiling.

Stockland places the proposal on industrial-zoned land in Western Sydney’s Mamre Road Precinct. Its project page says the design uses air-cooling technology that does not rely on water for cooling. A March 2026 endorsement from the NSW Investment Delivery Authority recognized the proposal as private-sector investment in critical sectors, including digital infrastructure.

What must the EIS prove?

The EIS must demonstrate the development’s ability to achieve a Power Usage Effectiveness score of 1.3 or less, equivalent to a five-star or better NABERS Data Centre Energy rating.

It must also address state targets for Water Usage Effectiveness. It must commit to matching operational electricity demand with NSW-based renewable energy supply at all times. These are assessment requirements, not measurements from an operating facility.

The EIS must model backup-power and cooling systems during unplanned outages, testing and maintenance. Noise and air-quality assessments must include cumulative effects from other proposed and approved data centers nearby. The State Significant Development assessment also includes separate work on traffic, water, biodiversity and utility infrastructure.

How large is Stockland’s wider platform?

Stockland’s October 19 operational update describes its data center opportunity as a partnership with global operator EdgeConneX, with roughly 450 MW of power secured across the platform. The company identifies four additional sites from its existing logistics pipeline.

Stockland says the platform-wide secured-power figure remains subject to final design, documentation and customer negotiations. The 360 MW number is an assessed IT load. The 444 MW number is a proposed campus maximum. The roughly 450 MW number is a portfolio-wide secured-power figure.

What other Sydney projects sit in the pipeline?

The Wetherill Park Data Centre record is at the Prepare SEARs stage and describes a single four-storey building operating 24/7, with approximately 238 MW of total capacity and 170 MW of IT load. The works include demolition and site establishment, an on-site substation and a transmission line.

Stockland’s update identifies Wetherill Park as 100% Stockland-owned and targeted at the same AI and hyperscaler customer category. A separate portal record for 192 Narellan Road in Campbelltown is at the Prepare EIS stage. It describes construction and 24/7 operation of a 100 MW data center, with a maximum building height of 30 meters.

Both projects remain earlier in the planning sequence than Kemps Creek’s public exhibition. The difference lies in process: Wetherill Park has preparing SEARs, while 192 Narellan Road is preparing an EIS. Kemps Creek has placed its EIS before the public.

What happens before construction?

Public submissions and the remaining assessment steps precede any construction decision, while Stockland anticipates a determination in 2027, a timing described as an expectation rather than a fixed approval date.

For Stockland, Kemps Creek is the immediate test of whether an AI and hyperscaler campus can satisfy NSW’s efficiency, renewable-energy and cumulative-impact requirements. The next proof points are the December 17 close of submissions, NSW’s assessment of efficiency and energy supply, and a determination Stockland expects in 2027.

Source: unite.ai

Share this article:

More from Daniel Okafor

Daniel Okafor

Show full bio

Correspondent covering money, funding and market shifts around entrepreneurship, startups and venture funding at Business Bearings.

2,400 articles

Related articles

« Previous article