US AI Chip Curbs May Slow Malaysia's 13GW Data Center Buildout
US export rules may delay Malaysian data center projects but leave the near-13GW pipeline intact, backed by 8.35GW in power agreements and 4.6GW of approved projects.
By Daniel Okafor
5 min read

What's News
- Malaysia’s near-term data center investment pipeline remains close to 13GW.
- The new US controls take effect Nov. 19, 2026, with a 90-day compliance window.
- Licensing applies above 12 million TPP, equivalent to about 758 Nvidia H200 GPUs.
- The pipeline includes 8.35GW of TNB energy supply agreements and 4.6GW of DCTF-approved projects.
- TNB’s Green Lane Pathway cut electricity connection timelines from 36 to 48 months to about 12 months.
By Daniel Okafor
Malaysia’s data center investment pipeline remains close to 13 gigawatts despite new US restrictions on advanced AI technology exports to five countries, including Malaysia, Hong Leong Investment Bank (HLIB) Research said in a Thursday note.
The bank called the development incrementally negative for Malaysia’s data center sector. Operators may delay projects while they assess licensing requirements, especially operators linked to Chinese hyperscalers.
Longer-term growth still rests on Malaysia’s electricity supply and infrastructure readiness. HLIB Research expects US hyperscalers and other non-Chinese entities to drive future demand.
What do the new US export controls require?
On Nov. 16, the US Commerce Department’s Bureau of Industry and Security (BIS) released an interim final rule. It seeks to prevent access to sensitive US AI technology from being circumvented through remote computing arrangements involving data centers in third countries.
BIS created two control sets: end-use and end-user restrictions, plus destination-based controls.
Under the end-use controls, licensing requirements cover exports, re-exports and in-country transfers to overseas data centers that remotely provide more than 12 million aggregate total processing performance, directly or indirectly, for companies headquartered in US arms-embargoed countries, including China and Macau.
The rule also requires data center operators, foreign semiconductor foundries and chip exporters to verify customer ownership and control. That due diligence covers links to entities or individuals from restricted countries.
Destination-based controls require licenses for exports, re-exports and in-country transfers of advanced semiconductors to Indonesia, Malaysia, Singapore, Thailand and Brazil. BIS identified those destinations as carrying a higher-than-normal risk of diversion.
Qualifying US-headquartered companies remain exempt from the additional licensing requirement, subject to reporting conditions. The rule takes effect on Nov. 19, 2026, with affected data center operators given 90 days to comply.
Can Malaysia’s 13GW pipeline survive the delay risk?
HLIB Research expects some operators to reassess projects and licensing obligations before committing to new capacity. The bank sees project delays and moderated investment momentum as the most immediate risks.
Neo-cloud players may withhold capacity expansion plans in the near term, HLIB Research said. Such restraint could slow investment in colocation data centers.
Malaysia is unlikely to face a significant disadvantage relative to other countries because the end-use restrictions can also affect data center operators elsewhere. The 12 million TPP threshold is relatively low.
That threshold equates to approximately 758 Nvidia H200 graphics processing units. Its reach therefore extends beyond operators serving Chinese-linked customers.
HLIB Research said the near-term pipeline “remained intact.” The bank cited 8.35GW of energy supply agreements (ESAs) with Tenaga Nasional Bhd (TNB) and 4.6GW of projects approved by the Data Centre Task Force (DCTF).
Can power access offset diverted investment?
HLIB Research also sees potential for investment “redirected from the Middle East and the US.” The bank linked scaled-back development in those markets to security concerns arising from the Iran war and post-US midterm election uncertainties.
Malaysia’s competitive edge partly rests on TNB’s Green Lane Pathway, introduced in August 2023. The initiative accelerates electricity connections for data center projects and cuts implementation timelines from 36 to 48 months to about 12 months.
Faster connections improve Malaysia’s ability to accommodate power-intensive facilities. The research house expects non-Chinese-linked entities to drive increasingly more demand for local capacity.
The Corporate Renewable Energy Supply Scheme (CRESS) Acceleration Package, launched in September 2026, gives data center investors another route to secure renewable energy directly from producers. It reduced the supply access charge from 20 sen per kilowatt-hour to 18 sen per kilowatt-hour.
HLIB Research believes the lower charge could make Malaysia more attractive to companies committed to RE100 targets, including Microsoft, Google, EdgeConneX and Amazon.
Where do project delays create earnings risk?
HLIB Research expects limited direct exposure for the construction sector because Chinese-linked data center developments typically engage China-based contractors. Major local contractors have secured most of their data center contracts from US hyperscalers, leaving them relatively insulated.
Power infrastructure companies face greater exposure. Project delays could defer contract awards and reduce near-term earnings visibility, according to HLIB Research.
The bank’s channel checks showed that the now-defunct AI Diffusion Rule previously delayed selected data center project awards by six to seven months. The new rules may produce a shorter but more targeted version of that disruption.
What do technology investors and utilities face?
HLIB Research sees minimal direct earnings risk for Malaysia’s technology sector. Exposure to AI remains largely indirect, and local players have no direct exposure to memory chips or AI GPUs.
The sector’s rally materialized only in the first half of 2026, later than global peers. Local technology players still benefit from China-plus-one supply-chain diversification across semiconductor capital equipment, outsourced semiconductor assembly and testing, and optical components.
However, HLIB Research warns that a broader de-rating of global semiconductor peers could pressure Malaysian stock valuations. It sees valuation, rather than earnings, as the more significant risk.
Slower capacity expansion among Chinese-linked data center operators could produce weaker-than-expected electricity demand growth, HLIB Research said. Demand from non-Chinese developers could offset that weakness.
TNB is expected to maintain its capital expenditure plans. HLIB Research sees that spending supporting the utility’s regulated asset base and future earnings growth.
For investors, the next checkpoint is whether non-Chinese demand keeps filling Malaysian capacity as Chinese-linked operators pause, while TNB sustains capital spending and local technology valuations hold.