Vietnam, South Korea and France win $423 million railway design deal

A five-company consortium won a $423 million design contract for Vietnam's planned 1,541-kilometer North-South high-speed railway, targeted to open in 2035.

By Daniel Okafor

3 min read

Vietnam-France-Korea consortium wins $423M design contract for Vietnam’s $67B high-speed railway
Vietnam-France-Korea consortium wins $423M design contract for Vietnam’s $67B high-speed railwayzheng2088 / pixabay

What's News

  • The design contract is worth KRW560 billion ($423 million) and was awarded on November 21.
  • The 30-month mandate runs from November 2026 to May 2029.
  • Five companies form the consortium: three from South Korea, one from France and one from Vietnam.
  • The planned railway covers about 1,541 kilometers and has a design speed of 350 kilometers per hour.
  • Construction is due in 2029, with opening targeted for 2035 at a total cost of $67.3 billion.

By Daniel Okafor

A Vietnam-South Korea-France consortium has won a KRW560 billion ($423 million) contract to study and design Vietnam’s North-South high-speed railway, South Korea’s Ministry of Land, Infrastructure and Transport said.

The ministry said in a Sunday statement that the contract was awarded on November 21. More than 40 rail design firms competed, according to the ministry. The five-company team combines three South Korean firms with one from France and one from Vietnam.

Who won the design contract?

The ministry identified five companies in the consortium:

  • Korea Rail Network Authority (KNR), Samboo Engineering and Yooshin Engineering, all from South Korea
  • SYSTRA, from France
  • Transport Engineering Design Incorporated (TEDI), from Vietnam

The ministry called the award “the largest overseas rail planning and design contract for South Korea.” Its statement also tied the win to support from the South Korean government.

The ministry said that support included two summits between the leaders of South Korea and Vietnam in August 2025 and April 2026. It also cited ministerial delegations in June and July 2026 and the delivery of a presidential letter.

How does the 30-month schedule work?

The consortium will conduct the feasibility study and basic design from November 2026 to May 2029. The ministry split the 30-month mandate into two phases:

  • 18 months for the feasibility study
  • 12 months for basic design

Feasibility work comes first. Basic design occupies the final 12 months. Under the ministry’s timetable, the contract ends in May 2029, the same year construction is due to begin.

The $423 million agreement covers study and design, not construction. The ministry said construction is due to start in 2029 and the line to open in 2035. The 30-month mandate therefore covers technical preparation before the planned construction program, rather than construction itself.

What will the railway look like?

The ministry’s full-project plan calls for a double-track high-speed line of about 1,541 kilometers from Hanoi to Ho Chi Minh City. The line’s design speed is 350 kilometers per hour.

The route has four sections:

  • Hanoi to Vinh: 281 kilometers
  • Vinh to Da Nang: 420 kilometers
  • Da Nang to Nha Trang: 480 kilometers
  • Nha Trang to Ho Chi Minh City: 360 kilometers

The Da Nang–Nha Trang section would be the longest, at 480 kilometers. The Hanoi–Vinh section would be the shortest, at 281 kilometers. Together, the four sections make up the roughly 1,541-kilometer corridor.

One basic-design program must cover all four sections. That makes the 18-month feasibility phase the gate for a design package spanning the entire route by May 2029. Any delay in either phase would narrow the runway to the planned 2029 construction start.

What is the financial exposure?

The ministry put the full railway’s cost at $67.3 billion. The $423 million design fee equals about 0.63% of that total, using the ministry’s figures.

Selection is complete: more than 40 firms competed, and the ministry awarded the work to a five-company consortium. The next test is delivery across the 18-month feasibility phase and the 12-month basic-design phase.

The schedule puts basic-design completion in May 2029 and construction in the same calendar year, leaving the design package as the immediate dependency for the planned construction start. If feasibility runs long, basic design has less room before that deadline. If the full design package slips, the 2029 construction start and 2035 opening target come under pressure.

The next observable checkpoint is the feasibility study. The consortium must finish that phase in 18 months and preserve the 12 months reserved for basic design. Any slippage would tighten the schedule linking a May 2029 design package, construction in 2029 and an opening targeted for 2035.

Source: technode.global

Share this article:

More from Daniel Okafor

Daniel Okafor

Show full bio

Correspondent covering money, funding and market shifts around entrepreneurship, startups and venture funding at Business Bearings.

2,604 articles

Related articles

« Previous articleNext article »