Malaysia Data Center Buildout Holds Despite US AI Chip Curbs Fear
UOB Kay Hian and RHB keep overweight ratings on Malaysian construction, saying US chip curbs fears drove a sell-off but the MYR 95.8 billion data center pipeline remains intact.
By Olivia Hart
4 min read

What's News
- Data center and cloud projects drew MYR 95.8 billion ($23.41 billion) in approved investments in H1 2026, 44% of Malaysia's total.
- Malaysia had 61 data center projects totaling 8,350MW of power demand as at end-June 2026; 19 projects worth about 2,700MW remain under development.
- Over RM11.8 billion in data center-related contracts went to UOB Kay Hian coverage companies in H2 2026 so far.
- 10 of the top 20 Johor non-residential contract awards by value in 2026 YTD came from China-linked players; only two went to local contractors.
- The rescinded Biden-era AI Diffusion Framework would have capped Malaysia at 50,000 GPUs over two years and 7% of operators' compute capacity.
Malaysia approved MYR 95.8 billion ($23.41 billion) in data center and cloud computing investments in the first half of 2026 — 44 percent of the country's total approved investments — and two major research houses say US chip export curbs will not derail the buildout. UOB Kay Hian and RHB Investment Bank maintained their overweight ratings on Malaysia's construction sector on Monday, even as fears over tighter US licensing rules for advanced AI chips triggered a sharp sell-off across construction stocks.
The sell-off reflects worry that stricter US controls, particularly on Nvidia's graphics processing units, could delay data center investments and construction timelines in Malaysia. UOB Kay Hian said in a research note that the primary objective of any tighter US regulations would likely be to prevent China-linked entities from accessing advanced AI chips and to curb transshipment from neighboring countries, including Malaysia, into China. The firm expects US-based hyperscalers that own and operate their own data centers in Malaysia to keep relatively uninterrupted access to AI chips, limiting the direct hit on local contractors.
How bad could the damage be?
RHB Investment Bank said the near- to medium-term impact should be manageable, because orders for AI chips supporting projects already under construction or nearing contract awards are likely to remain largely intact over the next six to 12 months. Existing chip bookings from hyperscalers and colocation providers support that view.
Diversification adds a buffer. Google is scaling up its in-house Tensor Processing Unit chips, while Microsoft plans to expand deployment of its homegrown Maia AI chips from 2027. That could mitigate Nvidia-related procurement disruptions and let major cloud providers sustain planned Malaysian expansion.
The caveat: colocation data centers serving China-related customers could face greater uncertainty if tighter controls disrupt procurement, financing or demand for computing capacity. UOB Kay Hian did not rule out delays for colocation-oriented developments with China-linked offtakers.
Exposure, however, looks limited on paper. RHB noted the proportion of contracts tied to colocation providers among major local contractors is small, and many of the largest data center contracts in Johor awarded to China-based players went to contractors headquartered in China. Its tracking showed 10 of the top 20 contract awards by value in Johor's non-residential category year to date in 2026 came from China-linked data center players — and only two of those 10 went to local builders. In plain terms: the sector most at risk is largely insulated from Malaysian contractors.
What does history say?
UOB Kay Hian drew parallels with the AI Diffusion Framework introduced under former US president Joe Biden's administration in January 2025 and rescinded in May that year. That framework classified Malaysia as a Tier 2 country, capping imports at 50,000 GPUs over two years and restricting data center operators to deploying a maximum of 7 percent of their computing capacity in the country.
Even under that threat, no major data center projects involving US hyperscalers were cancelled or significantly scaled back, because their AI chip procurement stayed largely uninterrupted. UOB Kay Hian said this offers reassurance that renewed regulatory concerns may not translate into widespread cancellations or a material deterioration in contractors' orderbooks.
Is the pipeline strong enough to hold?
The numbers suggest yes. According to the Malaysian Investment Development Authority (MIDA), Malaysia's total approved investments reached RM218.5 billion in H1 2026, up 12 percent year on year. As at end-June 2026, the country had 61 data center projects with total electricity demand of 8,350 megawatts. Of those, 42 projects with combined demand of 5,650MW were completed; the remaining 19 projects, roughly 2,700MW, were still under development.
Contract flows remain strong, with more than RM11.8 billion in data center-related contracts awarded to UOB Kay Hian's coverage companies in the second half of 2026 so far. The firm said the sector's record-high orderbook and multi-year earnings visibility underpin its positive stance, and that the actual impact of potential US chip restrictions was unlikely to be as severe as the market anticipated.
RHB flagged an upside for local colocation providers: as countries emphasize data sovereignty, with entire digital architectures required to sit physically within national borders, domestic providers could capture demand for locally hosted infrastructure and reduce reliance on foreign cloud platforms.
The risks have not disappeared. RHB cautioned that a substantial long-term slowdown in AI capital expenditure by US technology giants remains a key threat to Malaysia's data center expansion, alongside tighter AI chip export controls, project execution delays, and constraints in securing the power infrastructure that 8,350MW of planned capacity demands.
Source: technode.global