US chip curbs mostly spare Malaysia’s near-term data center pipeline

Malaysia’s data center construction pipeline should hold up despite U.S. chip controls, with Google, Microsoft and AWS backing near-term projects, MBSB Research said.

By Daniel Okafor

4 min read

US chip controls pose risks to future phases of Malaysia’s data center projects, but near-term pipeline intact, says MBS
US chip controls pose risks to future phases of Malaysia’s data center projects, but near-term pipeline intact, says MBSblickpixel / pixabay

What's News

  • Malaysian data center contract awards hit a record MYR 18.24 billion in calendar 2026, nearly double 2025.
  • SunCon’s MYR 10.5 billion to MYR 11 billion data center backlog equals 78% to 82% of its MYR 13.4 billion order book.
  • Google plans $15 billion for 2027-2028, Microsoft $2.2 billion over four years, and AWS $6.2 billion through 2038.
  • Awarded and visible US-hyperscaler projects over the next 12 months should remain largely intact, MBSB Research said.
  • The 13th Malaysia Plan includes MYR 430 billion for transport, water, the electricity grid and East Malaysia infrastructure.

By Daniel Okafor

Malaysian data center contract awards hit a record MYR 18.24 billion in calendar year 2026, nearly double 2025, MBSB Research said. The research house retained a positive outlook on construction, citing sustained sector activity.

“US chip controls mainly raise risks for future Chinese-linked phases; committed US-backed projects should remain intact,” MBSB Research said.

How do the chip controls affect projects?

In a Tuesday note, MBSB Research said the US Commerce Department introduced rules restricting prohibited users from remotely accessing advanced US chips through overseas data centers. MBSB said the move raises uncertainty over AI computing deployment in markets such as Malaysia.

The immediate pressure should fall on GPU deployment and capacity activation, MBSB said. Construction would suffer only if delays weaken tenant commitments or postpone subsequent development phases.

MBSB Research said owner-operated campuses serving established US hyperscalers appear better positioned for the rules than facilities tied to Chinese AI customers or less transparent GPU-as-a-Service arrangements.

MBSB Research said it expects projects already awarded and visible opportunities backed by US hyperscalers over the next 12 months to remain largely intact. Tighter checks of chip ownership, end-users and remote access could raise compliance requirements for future developments.

Which builders have the greatest exposure?

MBSB Research identified Sunway Construction Group Bhd (SunCon) as having the highest concentration. Gamuda Bhd, IJM Corp Bhd and Kerjaya Prospek Group Bhd have more diversified order books.

MBSB’s company-level estimates show:

  • Sunway Construction Group Bhd (SunCon): MBSB estimated outstanding data center works at MYR 10.5 billion to MYR 11 billion. That equals 78% to 82% of its MYR 13.4 billion order book, after estimated progress billings since June 2026.
  • SunCon customer mix: MBSB said its customers are predominantly US hyperscalers, alongside Singapore-based K2. Future order-book replenishment depends more on expansion by existing international customers than Chinese demand.
  • IJM Corp Bhd: MBSB estimated remaining data center works at MYR 1.8 billion to MYR 2.2 billion, or 12% to 15% of its MYR 14.5 billion order book. Google-linked projects in Elmina form a meaningful part of its exposure.
  • Kerjaya Prospek Group Bhd: Its maiden data center contract, worth MYR 858 million and largely unbilled, accounts for about 12% to 14% of its MYR 6 billion order book, MBSB said.
  • Gamuda Bhd: MBSB estimated outstanding data center works at MYR 6.5 billion to MYR 7 billion, or 9.8% to 10.6% of its MYR 66 billion order book. Its Google-linked campuses and broader infrastructure portfolio provide greater diversification against potential delays in future data center developments.

MBSB said colocation projects account for less than 1% of SunCon’s order book, around 0.6% for Gamuda Bhd and an immaterial portion for IJM Corp Bhd.

What underwrites near-term construction demand?

MBSB Research said continued investment by major US hyperscalers underpins Malaysia’s data center and related infrastructure pipeline.

  • Google: MBSB cited a plan to invest $15 billion in Malaysia during 2027 and 2028. The investment covers additional campuses in Selangor and Negeri Sembilan, more than 1 gigawatt (GW) of clean energy capacity and related water infrastructure.
  • Microsoft: The company has committed $2.2 billion over four years, according to MBSB. It is developing SEA3 in Johor as its second Malaysian cloud region.
  • Amazon Web Services (AWS): The company plans to invest $6.2 billion through 2038, MBSB said.

MBSB Research said these commitments provide visibility over near-term construction demand. It cautioned that tighter chip controls and scrutiny of AI investment returns could prompt hyperscalers to phase capital expenditure more cautiously, particularly for uncommitted expansion plans.

What could slow future awards?

MBSB Research said tighter US chip controls could slow the pace of future data center awards. It described public infrastructure replenishment as moderate after the principal Penang LRT packages. Upcoming water projects therefore matter as catalysts for the sector.

The research house also cited the MYR 430 billion development expenditure allocation under the 13th Malaysia Plan (13MP). MBSB said the allocation supports a broader medium-term pipeline spanning transport, water, the electricity grid and East Malaysia infrastructure.

MBSB’s next checkpoint is whether committed US-backed projects activate GPUs under tighter ownership, end-user and remote-access checks. Any slippage could weaken tenant commitments and later construction phases.

Source: technode.global

Share this article:

More from Daniel Okafor

Daniel Okafor

Show full bio

Correspondent covering money, funding and market shifts around entrepreneurship, startups and venture funding at Business Bearings.

2,189 articles

Related articles

« Previous articleNext article »