US Army Opens Land at Nine Bases for AI Data Centers — But Only With On-Site Power
The Army's November 2026 RFP seeks power generation at nine bases, with data centers allowed only as an option. Projects must back up host bases within one hour of grid failure for 14 days.
By Daniel Okafor
5 min read

What's News
- Proposals are due January 18, 2027; site tours run November 30 through December 17, 2026.
- Projects must deliver contingency power to host bases within one hour of a grid outage and sustain it for at least 14 days.
- Leases run 25 years under 10 U.S.C. § 2667; the Army invests no capital and buys no power or compute.
- Advanced nuclear up to 500 MW per unit, gas turbines, hydrogen, fuel cells, storage and solar are eligible technologies.
- Tooele's parcels include TCE-contaminated groundwater plumes; Blue Grass's 358-acre plot lacks water lines.
The U.S. Army issued a request for proposals on November 19, 2026 — dated November 20, 2026, according to law firm Holland & Knight — for commercial power generation facilities at nine military installations, with data centers permitted only as an option attached to power projects. Proposals for data centers alone will not be considered. Every bid must include generation that can deliver contingency electricity to the host base within one hour of a grid outage and sustain it for at least 14 continuous days.
The nine sites are:
- Blue Grass Army Depot, Kentucky — a major munitions storage facility
- Tooele Army Depot, Utah — an ammunition hub
- Sierra Army Depot, California — long-term equipment storage
- Fort Bragg, North Carolina
- Fort Hood, Texas
- Fort McCoy, Wisconsin
- Fort Rucker, Alabama
- Pine Bluff Arsenal, Arkansas
- Joint Base Lewis-McChord, Washington
Proposals are due January 18, 2027, at 5:00 p.m. ET. Site tours begin November 30 and run through December 17, with registration deadlines of November 25, December 2, and December 9 depending on the installation. Questions are due January 6, 2027.
Why did the Army flip to energy-first?
The solicitation marks a shift from earlier rounds that led with data center siting. In January 2025, the Army called for data center development on four bases. A June 2025 RFP sought power generation at seven eastern installations, with conditional awards at six announced in September.
In March 2026, the Army conditionally selected Carlyle for roughly 1,384 acres at Fort Bliss, Texas, and CyrusOne for about 1,201 acres at Dugway Proving Ground, Utah. Neither lease has been finalized.
Law firm Beveridge & Diamond, which analyzed the new solicitation, says the RFP reflects two realities: the nation needs new generation regardless of data center politics, and military installations may offer developers reduced exposure to local land-use restrictions and greater predictability in approvals.
The Army's first preference for any data center component is hardened facilities built to ICD 705 standards for Top Secret/IL6 workloads. The second preference is hyperscale AI and high-performance computing facilities targeting a power usage effectiveness of 1.15 or less.
What are the lease terms and developer obligations?
The Army will use its enhanced-use lease authority under 10 U.S.C. § 2667. Leases run an initial 25-year term with possible renewals. Consideration must equal or exceed fair market rental value, with a preference for in-kind contributions such as the resilience power itself.
Developers face three hard constraints:
- They must be U.S.-organized entities with majority domestic ownership and control.
- They must finance the full project lifecycle — environmental review, construction, operations, and decommissioning — without Army capital.
- The Army will not purchase power or computing capacity; developers must secure their own third-party offtakers.
Eligible generation technologies include advanced nuclear reactors of up to 500 MW per unit, natural gas turbines, fuel cells, hydrogen systems, battery storage, and solar paired with dispatchable generation and storage.
The Army may award one or more leases, and may select multiple offerors at the same installation if projects can be accommodated without conflict.
What site problems do developers inherit?
Several parcels carry significant environmental complications. At Blue Grass, the 358-acre plot has a 69 kV transmission line crossing it but lacks water distribution lines. Tooele's three parcels of 36, 96, and 500 acres include groundwater plumes contaminated with trichloroethylene, or TCE, on the smallest and largest plots, blocking new well drilling.
Sierra Army Depot's four parcels total 445 acres, served by Plumas Sierra Rural Electric Cooperative and a Tuscarora gas pipeline. Fort Bragg's three parcels of 385 acres are undeveloped mixed forest with high water risk; Duke Energy provides transmission and Piedmont Natural Gas has an adjacent pipeline. Fort Rucker offers 903 acres across three parcels with Alabama Power and Southeast Alabama Gas District service.
Documents for Fort McCoy, Fort Hood, and Joint Base Lewis-McChord were removed from the procurement notice, limiting public information on those sites.
Water use must be net-neutral or better, sourced from non-potable alternatives such as industrial grey water, treated municipal wastewater, or closed-loop cooling towers. Projects must avoid drawing on aquifers.
The leases are federal actions subject to NEPA, the National Historic Preservation Act, and the Endangered Species Act. Some installations operate under exclusive federal legislative jurisdiction, which may limit state and local regulatory authority. The RFP notes developers may still face state and local operational permitting requirements.
Does federal land insulate projects from politics?
Not entirely. The push to open federal land for data centers began under the Biden administration and has continued under the Trump administration. A July 2025 Trump executive order directed the Interior and Energy departments to offer authorizations for data center sites on lands they manage.
Senator Ruben Gallego has filed a defense-bill amendment that would bar new privately operated data centers on military installations, with exceptions for Defense Department national security facilities. It has not been voted on.
The RFP expressly requires data center developers to describe community outreach plans, assess potential opposition, and explain how they would address concerns — an acknowledgment that federal siting does not insulate projects from local pushback.
For developers, the calculus is whether the strategic advantages — predictable federal process, physical security, co-located generation, and potential relief from local opposition — outweigh federal leasing restrictions, environmental review, supply chain rules, and the need to bring their own customers and capital. The Army's stated objective in the RFP is blunt: maximize the financial return to the Department of the Army through the lease of non-excess available land on the installations.